( E : Engineering / P : Procument / PS : Procument Service / C : Construction / CS : Construction Supervision / GA : Government Approval )
사업 Reference
번호 Project Client Period Scope
201 ULSAN SRF BOILER STEAM SUPPLYING PROJECT (FLUE GAS TREATMENT EQUIPMENT DELIVERY/ INSTALLATION) DONGLIM E&G 2015.07~2016.02 E
200 MVR(MECHANICAL VAPOR RECOMPRESSION) STEPII PROJECT KUMHO P&B CHEM 2015.06~2016.04 E / P / C
199 P2 CVD HEAT RECOVERY SYSTEM MANUFACTURING & INSTALLATION OCI 2015.04~2015.10 E / P / C
198 KP-1 PLANT 2-LINE MVR(MECHANICAL VAPOR RECOMPRESSION) PROJECT KUMHO POLY CHEM 2015.04~2015.11 E / P / C
197 STT(II) BASIC ENGINEERING PACKAGE FOR EXTERNAL STORAGE FACILITY INSTALLATION SC ENG 2015.05~2015.05 E
196 THE 3 FACTORY RAW CONVERSION PROJECT DEOKYANG 2015.03~2015.12 E / P / C
195 MDI(METHYLENE DIPHENYL ISOCYANATE) & MDA MIXER, M-DA103 INSTALLATION KUMHO MITSUI CHEM 2015.05~2015.05 E / P / C
194 No.1 PMMA TANK INSTALLATION LG MMA 2015.02~2015.07 E / P / C
193 NEW C4 BALL TANK(3,000㎥) INSTALLATION KUMHO PETRO CHEM 2015.01~2015.12 E / P / C
192 PB(POLY BUTANE)2 PLANT 75,000 MTA REVAMPING PROJECT DAELIM INDUSTRIAL 2014.11~2016.05 E / P / C
191 COC(COCL2) REACTOR & HCL ADSORPTION TOWER INSTALLATION KUMHO MITSUI CHEM 2014.11~2015.05 E / P / C
190 POLY SILICON CAPA-UP DETAIL DESIGN HANWHA CHEM 2014.11~2015.08 E
189 TECHNICAL RESEARCH INSTITUTE UTILITY DETAILED DESIGN S-OIL 2014.11~2015.12 E
188 MVR(MECHANICAL VAPOR RECOMPRESSION) INSTALLATION SAMSUNG TECHWIN 2014.11~2014.11 E / P / C
187 BASIC DESIGN FOR HEATING MEDIUM BOILER PROCESS HUVIS 2014.10~2015.05 E
186 MEG 50,000TPA DEBOTTLENECKING PROJECT LOTTE E&C 2014.10~2016.09 E / P / C
185 CR-MDI(METHYLENE DIPHENYL ISOCYANATE) STORAGE TANK KUMHO MITSUI CHEM 2014.10~2014.12 E / P / C
184 ANIMAL WASTE RECYCLING PROJECT G&L/BLUE O&M 2014.09~2015.09 E
183 CO2 LIQUEFIED FACILITY PLANT ENGINEERING DEOKYANG 2014.09~2014.11 E
182 IPC REACTOR AND AUXILIARY EQUIPMENT REPLACEMENT WORK KUMHO MITSUI CHEM 2014.08~2014.12 E / P / C
181 IPC WASTE GAS TREATMENT FACILITY INSTALLATION WORK KUMHO MITSUI CHEM 2014.08~2014.12 E / P / C
180 UGCC ETHYLENE PLANT PIPING/INSTR. FIELD ENGINEERING GS E&C 2014.08~2015.09 FE
179 3RD Hx REFINE PROCESS IMPROVEMENT PROJECT KOREA PETRO CHEM 2014.08~2015.12 E
178 DETAIL DESIGN FOR PE2, LP-2M-LLD PRODUCTION FACILITY HANWHA CHEM 2014.07~2014.09 E
177 CURRENTIZATION OF RELAY DRAWINGS YNCC 2014.07~2014.12 E
176 ELEC./INSTR./CIVIL DESIGN OF 2014 NCC(NAPHTHA CRACKING CENTER) UTILITY AREA EXPANSION PROJECT LG TOYO ENG 2014.07~2014.12 E
175 H-PC, EFFICIENCY IMPROVEMENT LOTTE CHEM 2014.07~2015.01 E / P / C
174 DETAIL DESIGN FOR SPP(SUPER ABSORBENT POLYMER PILOT) PROJECT WOOYANG HC 2014.06~2014.12 E
173 TPEE(THERMOPLASTIC EASTER ELASTOMER) PROJECT SAMYANG 2014.05~2015.12 E
172 DETAIL DESIGN FOR H2 BOOSTING COMPRESSOR INSTALLATION SPG CHEM 2014.04~2014.12 E